DIGGIN' DOWNTOWN UPDATE - 5/16

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 16, 2025

Recent Weeks:

Storm Sewer Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Saturday 5/17 – Contractor to be on site to continue paving operations on Washington Street.

Monday 5/19 to Friday 5/23 – Contractor to continue paving operations, begin sidewalk installation, and begin subdrain installation on east side of Washington Street. Contractor to begin subdrain installation and subgrade preparation on west side of Washington Street.

Phase 1B Main Street

Monday 5/19 to Friday 5/23 Contractor to complete pavement removals on Main Street.

Looking Ahead:

Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...