DIGGIN' DOWNTOWN UPDATE - 5/23

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 23, 2025


Recent Weeks:

Subdrain Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to continue subdrain installation and prepare for paving at intersection of Fillmore and Washington Street.

Phase 1B Main Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to begin storm sewer utility work.

Looking Ahead: Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...