DIGGIN DOWNTOWN UPDATE - 6/13

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: June 13, 2025 
Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)
Storm Sewer Installation (Main Street)

Next Week:
Phase 1A Washington Street
Monday 6/16 to Friday 6/20 – Final touches on PCC pavement work on Washington Street West of the Fillmore Intersection
Contractor to continue driveway, sidewalk, curb and gutter for Washington Street East of Fillmore Intersection
Subbase and subdrain operations in preparation for permeable pavers

Phase 1B Main Street
Monday 6/16 to Friday 6/20– Contractor to continue storm sewer utility installation and begin water main installation.

Looking Ahead:
Washington Street will remain closed as paving operations and permeable paver preparation continue throughout the following weeks. Main Street will remain closed for utility installation.
Tentative Schedule - The week of July 7 to begin installation of sanitary and water service lines to the buildings along Main Street (this is when sidewalk and water interruptions would occur).
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...