DIGGIN' DOWNTOWN UPDATE - 7/3

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: July 3, 2025

Recent Weeks:

Concrete Paving Operations (Washington St)

Permeable Paver Installation (Washington St)

Storm Sewer installation (Washington Street/Main Street)

General Site Cleanup (Prior to 4th of July Celebration)

West Washington Intersection Opened  (Washington Street)

Next Week:

Phase 1A Washington Street

Monday 7/7 to Friday 7/11 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.

Phase 1B Main Street

Monday 7/7 to Friday 7/11 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street. Contractor will move to utility installation along East Washington Street toward the end of the week.

*Scheduled water service interruption along Main Street will occur on Monday July 7.

Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...