DIGGIN' DOWNTOWN UPDATE - 7/18

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: July 18, 2025

Recent Weeks:

(Washington Street/Main Street)

Storm Sewer installation

Permeable Paver Installation (Washington St)

Concrete Paving Operations (Washington St)


Next Week:

Phase 1A Washington Street

Monday 7/21 to Friday 7/25 – Contractor to continue permeable paver and subdrain installation along Washington Street.

Phase 1B Main Street

Monday 7/21 to Friday 7/25 – Sanitary Sewer installation will begin along Washington Street east of Main Street. Contractor will move to water main installation at the intersection of Washington Street and Main Street toward the end of the week.

Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.



Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...