DIGGIN DOWNTOWN UPDATE - 8/22

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 22, 2025

 Recent Weeks:

Pavement Removals (Jefferson & Main Intersection)

Underground Utility Installation (Main St)

Subgrade Preparation (East Washington St)

Washington Street West of the Main Street Intersection has opened                                                      

 Next Week:

Phase 1A Washington Street

Monday 8/25 to Friday 8/29 – Contractor to complete subbase and subdrain installation along East Washington Street.

Phase 1B Main Street

Monday 8/25 to Friday 8/29 – Contractor to continue sanitary service replacements and begin water service replacements along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.

Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...