Diggin' Downtown Update - 10/3

Last Updated 10/20/2025Posted in DIGGIN' DOWNTOWN

Date: October 3, 2025

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Lighting System Installation (Washington St/Main St)

Paving Operations (Main St)


Next Week:

Phase 1A Washington Street/Main Street

Monday 10/6 to Friday 10/10 

Contractor to install sidewalk ramps at intersection of Washington and Main Street. Contractor will then begin subdrain and curb and gutter installation along Main Street.

Phase 1B Jefferson Street

Monday 10/6 to Friday 10/10 

Contractor to complete storm sewer and sanitary sewer installation along East Jefferson Street.

Looking Ahead:

Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...