Diggin Downtown Update 11/21

Last Updated 11/24/2025Posted in DIGGIN' DOWNTOWN

Date: November 21, 2025


Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Subgrade Compaction, Subbase, Subdrain Installation, Paving

(Main St/East Jefferson St)


Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 11/24 to Wednesday 11/26 – Contractor to continue earthwork, compaction, subdrain installation, and paving operations.

Thursday 11/27 to Friday 11/28 – No major work anticipated due to the holiday. Contractor may be onsite for minor sitework.

Phase 2A Jefferson Street.

Monday 11/24 to Wednesday 11/26 Contractor to work on storm sewer installation.

Thursday 11/27 to Friday 11/28 – No major work anticipated due to the holiday. Contractor may be onsite for minor sitework.

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.


Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...