DIGGIN DOWNTOWN UPDATE - 2/6/26

Last Updated 2/9/2026Posted in DIGGIN' DOWNTOWN

Date: February 6, 2026

Recent Weeks:

Sanitary Sewer Installation (Jefferson St)

Pavement Removal (Fillmore St)

Next Week:

Phase 2A Jefferson Street.

Monday 2/9 to Friday 2/13 – Contractor to continue roadway and sidewalk paving.

Phase 2B Fillmore Street.

Monday 2/9 to Friday 2/13 – Contractor to begin water main installation on the east side of Fillmore Street.

Looking Ahead:

Jefferson Street between Main Street and Fillmore Street will remain closed for roadway installation.  Fillmore Street is expected to fully close February 16 (weather dependent).

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...