DIGGIN DOWNTOWN UPDATE - 2/16/26

Last Updated 2/16/2026Posted in DIGGIN' DOWNTOWN

Date: February 13, 2026 

Recent Weeks:
Water Main Installation (Fillmore St)
Pavement Removal (Fillmore St)
Paving Preparation and Installation (Jefferson St)

Next Week:
Phase 2A Jefferson Street.
Monday 2/16 to Friday 2/20 Contractor to continue roadway and sidewalk paving.
Phase 2B Fillmore Street.
Monday 2/16 to Friday 2/20 – Contractor to continue water main installation on the east side of Fillmore Street. All of Fillmore Street will be closing this week.

Looking Ahead:
Jefferson Street between Main Street and Fillmore Street will remain closed for roadway installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...