Recent Weeks:
Water Service Installation (Fillmore St)
Paving Preparation and Installation (Jefferson St)

Next Week:
Phase 2A Jefferson Street.
Monday 3/2 to Friday 3/6 – Contractor to continue permeable paver installation, sidewalk paving, and curb and gutter installation.

Phase 2B Fillmore Street.
Monday 3/2 to Friday 3/6 – Contractor to complete water service installation and begin working on sanitary service installations.

Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...