DIGGIN DOWNTOWN 3/6

Last Updated 3/9/2026Posted in DIGGIN' DOWNTOWN

Date: March 6, 2026

 

Recent Weeks:

Water Service Installation (Fillmore St)

Sanitary Sewer Service Installation (Fillmore St)

Paving Preparation and Installation (Jefferson St)

Permeable Paver Installation (Jefferson St)


Next Week:

Phase 2A Jefferson Street.

Monday 3/9 to Friday 3/13 – Curb and gutter, permeable paver aggregate, and sidewalk installation.

Phase 2B Fillmore Street.

Monday 3/9 to Friday 3/13 – Complete sanitary sewer service installation. Begin storm sewer installation


Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.


Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...