DIGGIN DOWNTOWN UPDATE - 5/1

Last Updated 5/26/2026Posted in DIGGIN' DOWNTOWN

Date: May 1, 2026

Recent Weeks:

Sanitary Sewer/Water Main Installation (Fillmore St)

Mainline Paving (Fillmore St)

Next Week:

Phase 2B Fillmore Street.

Monday 5/4 to Friday 5/8:

·         Continue roadway paving

·         Begin Excavation in permeable paver locations.

·         Continue utility installation in Fillmore/Jefferson intersection

Looking Ahead:

Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...