DIGGIN' DOWNTOWN UPDATE - 3/7

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: March 7, 2025

Recent Weeks:

Water Main Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 3/10 – Contractor will begin installing water services along Washington Street on the west side of Fillmore Street.

Tuesday 3/11 – Contractor will complete installation of water services along Washington Street on the west side of Filmore Street. Contractor to begin sidewalk removals in front of fire station to complete fire station water service installation.

Wednesday 3/12 to Friday 3/14 – Contractor to begin sidewalk removals and water service installations in front of businesses on north side of Washington Street.

*Please Note –Sections of sidewalk will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as utility installation continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...