DIGGIN' DOWNTOWN UPDATE - 2/7

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: February 7, 2025

Recent Weeks:

Water Main Installation.

Light poles to be removed.

Connect new water line to both hydrants.


Next Week:

Mon-Wed testing water main

Thursday, February 13 all of Washington Street to be closed for remainder of Washington Street project.

Pavement removal to begin on February 13 to prepare for watermain service connections to buildings.

 

Looking Ahead:

Week of February 17 new watermain services to be connected to buildings.  This will involve partial sidewalk removal with rock to back fill the area once completed.

 After the water services to the buildings’ are complete they will start on the storm system.

Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...