DIGGIN' DOWNTOWN UPDATE - 4/4

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 4, 2025

Recent Weeks:

Sanitary Sewer Installation

Manhole Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 4/7 to Tuesday 4/8 – Contractor to begin storm sewer installation along Washington Street.

Wednesday 4/9 to Friday 4/11 – Contractor will continue storm sewer installation along Washington Street, as well as begin preparation for sidewalk installation on the north side of Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...