DIGGIN' DOWNTOWN UPDATE - 5/30

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: May 30, 2025 

Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)

Next Week:
Phase 1A Washington Street Monday 6/2 to Friday 6/6 – Contractor to continue subdrain installation and concrete paving along Washington Street.

Phase 1B Main Street Monday 6/2 to Friday 6/6– Contractor to install storm sewer utility.

Looking Ahead:
Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...