DIGGIN DOWNTOWN UPDATE - 7/25

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: July 25, 2025

 Recent Weeks:

Concrete Paving Operations (Washington St)

Permeable Paver Installation (Washington St)

Storm Sewer installation (Washington Street/Main Street)

Water Main Installation (Washington Street/Main Street)

Next Week:

Phase 1A Washington Street

Monday 7/28 to Friday 8/1 – Contractor to continue permeable paver and sidewalk installation along Washington Street. Subgrade prep on Main/Washington Intersection.

Phase 1B Main Street

Monday 7/28 to Friday 8/1 – Contractor to continue water main and water service installation along East Washington Street.

Looking Ahead:

Washington Street will remain closed as sidewalk and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.


DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...