DIGGIN DOWNTOWN UPDATE - 8/8

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: August 8, 2025 
Recent Weeks:
Concrete Paving Operations (Washington & Main St)
Underground Utility Installation (Washington Street/Main Street)


Next Week:
Phase 1A Washington Street
Monday 8/11 to Friday 8/15 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street

Phase 1B Main Street
Monday 8/11 to Friday 8/15 – Contractor to continue water main installation along Main Street.

Looking Ahead:
Week of August 11 and 18: Water main installation on Main Street and paving operations on East Washington
Week of August 25: Jefferson/Main Intersection and East Jefferson closed for removals. Water services for Main Street businesses.
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...