DIGGIN DOWNTOWN UPDATE - 9/12

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: September 12, 2025

Recent Weeks:
Underground Utility Service (Main St)
Paving Operations (E Washington St, Washington & Main Street Intersection and Main Street)
East Washington Street is open to the intersection Water line service replacement completed on Main Street
 
Next Week:
Phase 1A Washington Street
Monday 9/15 to Friday 9/19 – Contractor to continue paving operations at intersection of Washington Street and Main Street and sidewalk installation along Main Street.
*Please note – Sections of sidewalk along Main Street will be inaccessible while new sidewalks are being formed and poured.

Phase 1B Main Street/Jefferson Street.
Monday 9/15 to Friday 9/19 – Contractor to continue sanitary sewer service installation then will move to storm sewer installation in the Jefferson/Main intersection. Alliant Energy continues to replace gas line along East Jefferson. Looking Ahead:

Looking Ahead:
Washington and Main Street intersection will remain closed for paving operations. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. East Jefferson will remain closed for utility installation.
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...