DIGGIN' DOWNTOWN UPDATE - 9/26

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: September 26, 2025 

Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Water Main Installation (E Jefferson St)
Paving Operations (Main St/Washington St)
Light Pole Base Installation (Main Street)

Next Week:
Phase 1A Washington Street/Main Street
Monday 9/29 to Friday 10/3 – Contractor to continue paving operations along Main Street.
Phase 1B Main Street/Jefferson Street.
Monday 9/29 to Friday 10/3 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection for paving operations. East Jefferson will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...