DIGGIN DOWNTOWN UPDATE - 10/24

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: October 24, 2025

 

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Curb and Gutter installation (Main St)

Permeable Paver installation (Main St)

Pavement Removals (Jefferson St)

 

Next Week:

Phase 1B Main Street

Monday 10/27 to Friday 10/31 – Contractor to complete permeable paver installation and continue sidewalk installation on Main Street.

Phase 1B Main Street/East Jefferson Street.

Monday 10/27 to Friday 10/31 – Contractor to complete storm sewer installation in the intersection and continue water and sanitary sewer installation along East Jefferson Street

Phase 2A Jefferson Street.

Monday 10/27 to Friday 10/31 Contractor to continue pavement removals along Jefferson Street up to the intersection with Fillmore Street

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. Jefferson Street between Main Street and Fillmore Street will remain closed for pavement removal.

DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...
DIGGIN DOWNTOWN UPDATE - 5/16Date: May 22, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Next Week: P...
DIGGIN DOWNTOWN UPDATE - 5/15Date: May 15, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Subdrain Installation Paving (Fillmore St) Curb and Gut...
Osceola Recognized at 2026 Main Street Iowa Development ... Osceola received statewide recognition at the 2026 Main Street Iowa Development Awards, held May 8 in West Des Moines as Main Street Iow...