DIGGIN DOWNTOWN UPDATE - 11/7

Last Updated 11/10/2025 • Posted in DIGGIN' DOWNTOWN

Date: November 7, 2025

Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Permeable Paver installation (Main St)

Sidewalk Installation (Main Street)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 11/10 to Friday 11/14 – Contractor to begin earthwork, compaction, and subdrain installation.

Phase 2A Jefferson Street.

Monday 11/10 to Friday 11/14 – Contractor to continue water main installation.

Looking Ahead:

East Jefferson to the Main Street intersection to remain closed for pavement operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

Downtown Spooktacular Brings Halloween Fun to the Square!What a SPOOKTACULAR night in Downtown Osceola! Our annual Downtown Spooktacular on Friday, October 23, brought families, friends, and pl...
DIGGIN DOWNTOWN UPDATE - 6/19Date: June 19, 2026 Recent Weeks: The square is now all open to traffic! Sidewalk Installation (Fillmore St) Light Pole Installation (Fi...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...