DIGGIN DOWNTOWN UPDATE - 12/19

Last Updated 12/22/2025Posted in DIGGIN' DOWNTOWN

Date: December 19, 2025

Recent Weeks:
Underground Utility Service Installation (Jefferson St)
Sidewalk Installation (Main St/East Jefferson St)
Main Street & East Jefferson is Now Open

Next Week: Phase 2A Jefferson Street.
Monday 12/22 to Wednesday 12/24– Contractor to continue sanitary sewer installation and begin sidewalk installation west of Main/Jefferson intersection.
Thursday 12/25 – No work anticipated on site.
Friday 12/26 – Contractor may be on site to continue sidewalk installation.

Looking Ahead:
West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation. All of Fillmore Street is anticipated to close in January (weather dependent).

DIGGIN DOWNTOWN UPDATE - 6/19Date: June 19, 2026 Recent Weeks: The square is now all open to traffic! Sidewalk Installation (Fillmore St) Light Pole Installation (Fi...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...