DIGGIN DOWNTOWN UPDATE - 1/9/26

Last Updated 1/13/2026Posted in DIGGIN' DOWNTOWN

Date: January 9, 2026 
Recent Weeks:
Sanitary Sewer Installation (Jefferson St) Sidewalk Installation (Jefferson St)


Next Week:
Phase 2A Jefferson Street.
Monday 1/12 to Friday 1/16– Contractor to continue sanitary sewer installation and begin roadway earthwork and subdrain installation.
Looking Ahead: 
Jefferson Street between Main Street and Fillmore Street will remain closed for utility and roadway installation. Fillmore Street is expected to fully close late January/early February (weather dependent).
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...