DIGGIN DOWNTOWN UPDATE - 4/3
Date: April 3, 2026
Recent Weeks:
Storm Sewer Installation (Fillmore St)
Pavement Removal (Fillmore St)
Permeable Paver Installation (Jefferson St)
Sidewalk Installation (Jefferson St)
Light Pole Installation (Jefferson St)
Next Week:
Phase 2A Jefferson Street.
Monday 4/6 to Friday 4/10:
· Install remaining sections of sidewalk, ramps, bench pads.
· Install permeable pavers.
· Install streetlights.
Phase 2B Fillmore Street.
Monday 4/6 to Friday 4/10:
· Continue storm sewer installation.
· Begin utility installation in Fillmore/Jefferson intersection.
Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.


.jpg)