DIGGIN DOWNTOWN UPDATE - 4/24
Date: April 24, 2026
Recent Weeks:
Sanitary Sewer/Water Main Installation (Fillmore St)
Paving Preparation (Fillmore St)
Next Week:
Phase 2A Jefferson Street.
Monday 4/27 to Friday 5/1:
· Install light poles
Phase 2B Fillmore Street.
Monday 4/27 to Friday 5/1:
· Continue roadway paving
· Continue utility installation in Fillmore/Jefferson intersection
· Install electrical conduit
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.