DIGGIN DOWNTOWN UPDATE - 5/8
Date: May 8, 2026
Recent Weeks:
Storm Sewer Installation (Fillmore St)
Mainline Paving (Fillmore St)
Permeable Paver Installation (Fillmore St)
Next Week:
Phase 2B Fillmore Street.
Monday 5/11 to Friday 5/15:
• Continue excavation and rock installation in permeable paver locations.
• Continue subdrain and curb and gutter installation.
• Continue utility installation in Fillmore/Jefferson intersection.
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.