DIGGIN DOWNTOWN UPDATE - 5/15

Last Updated 5/26/2026Posted in DIGGIN' DOWNTOWN

Date: May 15, 2026

 

Recent Weeks:

Permeable Paver Rock Installation (Fillmore St)

Subdrain Installation Paving (Fillmore St)

Curb and Gutter Installation (Fillmore St)

All storm, sewer and water utility work has been completed.


Next Week:

Phase 2B Fillmore Street.

Monday 5/18 to Friday 5/22:

Curb and gutter installation on west side.

Sidewalk installation on east side.

Light pole base installation.

Begin concrete preparation in Fillmore/Jefferson intersection.


Looking Ahead:

Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.

DIGGIN DOWNTOWN UPDATE - 5/16Date: May 22, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Next Week: P...
DIGGIN DOWNTOWN UPDATE - 5/8Date: May 8, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Mainline Paving (Fillmore St) Permeable Paver Installation (Fillm...
DIGGIN DOWNTOWN UPDATE - 5/1Date: May 1, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Mainline Paving (Fillmore St) Next Week: Phase 2B F...
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...