DIGGIN' DOWNTOWN UPDATE - 1/3

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: January 3, 2025

Recent Weeks:

·         General site set up and safety fence installation

·         Pavement removal

·         Existing utility investigation

Next Week:

Phase 1A Washington Street

·         No work scheduled for next week due to low temperatures.

Looking Ahead:

·         Water main construction will continue through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...