DIGGIN' DOWNTOWN UPDATE - 1/3

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: January 3, 2025

Recent Weeks:

·         General site set up and safety fence installation

·         Pavement removal

·         Existing utility investigation

Next Week:

Phase 1A Washington Street

·         No work scheduled for next week due to low temperatures.

Looking Ahead:

·         Water main construction will continue through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...