Date: February 7, 2025

Recent Weeks:

Water Main Installation.

Light poles to be removed.

Connect new water line to both hydrants.


Next Week:

Mon-Wed testing water main

Thursday, February 13 all of Washington Street to be closed for remainder of Washington Street project.

Pavement removal to begin on February 13 to prepare for watermain service connections to buildings.

 

Looking Ahead:

Week of February 17 new watermain services to be connected to buildings.  This will involve partial sidewalk removal with rock to back fill the area once completed.

 After the water services to the buildings’ are complete they will start on the storm system.

Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...