Recent Weeks:

Water Main Installation.

Light poles to be removed.

Connect new water line to both hydrants.


Next Week:

Mon-Wed testing water main

Thursday, February 13 all of Washington Street to be closed for remainder of Washington Street project.

Pavement removal to begin on February 13 to prepare for watermain service connections to buildings.

 

Looking Ahead:

Week of February 17 new watermain services to be connected to buildings.  This will involve partial sidewalk removal with rock to back fill the area once completed.

 After the water services to the buildings’ are complete they will start on the storm system.

Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...