Recent Weeks:

Water Main Installation.

Light poles to be removed.

Connect new water line to both hydrants.


Next Week:

Mon-Wed testing water main

Thursday, February 13 all of Washington Street to be closed for remainder of Washington Street project.

Pavement removal to begin on February 13 to prepare for watermain service connections to buildings.

 

Looking Ahead:

Week of February 17 new watermain services to be connected to buildings.  This will involve partial sidewalk removal with rock to back fill the area once completed.

 After the water services to the buildings’ are complete they will start on the storm system.

Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/
DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...