DIGGIN' DOWNTOWN UPDATE - 2/21

Last Updated 4/4/2025Posted in DIGGIN' DOWNTOWN

Date: February 21, 2025

Recent Weeks:

-Water Main Installation

-No work week (2/17) due to low temperatures

Next Week:

Phase 1A Washington Street

Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.

Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.

Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.

*Please NoteSections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...
Welcome to Osceola, Droppett! | Ribbon Cutting + Coffee... On May 15,we had the pleasure of officially welcoming Droppett to Osceola with a celebratory Ribbon Cutting and Coffee Connections event...