Recent Weeks:

-Water Main Installation

-No work week (2/17) due to low temperatures

Next Week:

Phase 1A Washington Street

Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.

Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.

Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.

*Please NoteSections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...