DIGGIN' DOWNTOWN UPDATE - 3/7

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: March 7, 2025

Recent Weeks:

Water Main Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 3/10 – Contractor will begin installing water services along Washington Street on the west side of Fillmore Street.

Tuesday 3/11 – Contractor will complete installation of water services along Washington Street on the west side of Filmore Street. Contractor to begin sidewalk removals in front of fire station to complete fire station water service installation.

Wednesday 3/12 to Friday 3/14 – Contractor to begin sidewalk removals and water service installations in front of businesses on north side of Washington Street.

*Please Note –Sections of sidewalk will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as utility installation continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...