DIGGIN' DOWNTOWN UPDATE - 3/7

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: March 7, 2025

Recent Weeks:

Water Main Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 3/10 – Contractor will begin installing water services along Washington Street on the west side of Fillmore Street.

Tuesday 3/11 – Contractor will complete installation of water services along Washington Street on the west side of Filmore Street. Contractor to begin sidewalk removals in front of fire station to complete fire station water service installation.

Wednesday 3/12 to Friday 3/14 – Contractor to begin sidewalk removals and water service installations in front of businesses on north side of Washington Street.

*Please Note –Sections of sidewalk will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as utility installation continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...
DIGGIN' DOWNTOWN UPDATE - 7/18Date: July 18, 2025 Recent Weeks: (Washington Street/Main Street) Storm Sewer installation Permeable Paver Installation (Washington St) ...
DIGGIN' DOWNTOWN UPDATE - 7/11Date: July 11, 2025 Recent Weeks: Roadway Extended East to Intersection (Washington St) Permeable Paver Installation (Washington St) Wes...