Recent Weeks:

Water main and service installation.

Light poles on Washington Street Removed.

Washington Street watermain connected to Main Street waterline to maintain water pressure and fire flows throughout the city.

This Week:

Phase 1A Washington Street

Monday 3/24 – Contractor completed final water main tie in at west end of Washington Street.

Tuesday 3/25 to Friday 3/28 – Contractor will install new sanitary sewer services along Washington Street.

Looking Ahead:

Washington Street will remain closed as sanitary and storm sewer installation continues through the following weeks.

New sidewalks are expected to be installed mid-week next week along the building fronts.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...