DIGGIN' DOWNTOWN UPDATE - 3/21

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: March 21, 2025

Recent Weeks:

Water main and service installation.

Light poles on Washington Street Removed.

Washington Street watermain connected to Main Street waterline to maintain water pressure and fire flows throughout the city.

This Week:

Phase 1A Washington Street

Monday 3/24 – Contractor completed final water main tie in at west end of Washington Street.

Tuesday 3/25 to Friday 3/28 – Contractor will install new sanitary sewer services along Washington Street.

Looking Ahead:

Washington Street will remain closed as sanitary and storm sewer installation continues through the following weeks.

New sidewalks are expected to be installed mid-week next week along the building fronts.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...