DIGGIN' DOWNTOWN UPDATE - 3-28
Date: March 28, 2025
Recent Weeks:
-Sanitary sewer service installation
-Water main installation and water main services completed on Washington Street.
Next Week:
Phase 1A Washington Street
-Monday 3/31 to Wednesday 4/2 – Contractor will finish sanitary sewer service installations as well as replace existing sanitary sewer manholes along Washington Street.
-Thursday 4/3 to Friday 4/4 – Contractor will begin storm sewer installation along Washington Street.
-Sidewalk preparation may begin this week, contingent upon the completion of sanitary sewer installations.
Looking Ahead:
-Washington Street will remain closed as storm sewer installation continues through the following weeks.
- Main Street is expected to close within the next 3-4 weeks following the completion of the storm sewer installation.
Follow along here to see the latest progress!
Project Facebook Page: