Recent Weeks:

-Sanitary sewer service installation

-Water main installation and water main services completed on Washington Street.

Next Week:

Phase 1A Washington Street

-Monday 3/31 to Wednesday 4/2 – Contractor will finish sanitary sewer service installations as well as replace existing sanitary sewer manholes along Washington Street.

-Thursday 4/3 to Friday 4/4 – Contractor will begin storm sewer installation along Washington Street.

-Sidewalk preparation may begin this week, contingent upon the completion of sanitary sewer installations.

Looking Ahead:

-Washington Street will remain closed as storm sewer installation continues through the following weeks.

- Main Street is expected to close within the next 3-4 weeks following the completion of the storm sewer installation.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...