DIGGIN' DOWNTOWN UPDATE - 4/11

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 11, 2025
This Past Week:
Storm Sewer Installation
Sidewalk Installation
Next Week:
Phase 1A Washington Street
Monday 4/14 to Friday 4/18 – Contractor to continue storm sewer and sidewalk installations along Washington Street.
Looking Ahead:
Washington Street will remain closed as storm sewer installation continues through the following weeks.
Pavement preparation along Washington Street to begin after storm sewer installation. Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...