DIGGIN' DOWNTOWN UPDATE - 4/18

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 18, 2025

Recent Weeks:

Storm Sewer Installation

Sidewalk Installation

ADA Accessible Ramps Poured

Next Week:

Phase 1A Washington Street

Monday 4/21 to Friday 4/25 – Contractor to continue storm sewer installation along Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

In the upcoming weeks Main Street will be closed for pavement removal.

Once the utility crew finishes installing the storm sewer along Washington Street, they will shift their focus to Main Street to begin installing the new water main. Meanwhile, on Washington Street TK Concrete will focus on surface improvements, including road preparation, pouring new pavement, completing the remaining sidewalks, and installing permeable pavers in the on-street parking areas.

Follow along here to see the latest progress!

Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...