DIGGIN' DOWNTOWN UPDATE - 4/18

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 18, 2025

Recent Weeks:

Storm Sewer Installation

Sidewalk Installation

ADA Accessible Ramps Poured

Next Week:

Phase 1A Washington Street

Monday 4/21 to Friday 4/25 – Contractor to continue storm sewer installation along Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

In the upcoming weeks Main Street will be closed for pavement removal.

Once the utility crew finishes installing the storm sewer along Washington Street, they will shift their focus to Main Street to begin installing the new water main. Meanwhile, on Washington Street TK Concrete will focus on surface improvements, including road preparation, pouring new pavement, completing the remaining sidewalks, and installing permeable pavers in the on-street parking areas.

Follow along here to see the latest progress!

DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...