DIGGIN' DOWNTOWN UPDATE - 4/18

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 18, 2025

Recent Weeks:

Storm Sewer Installation

Sidewalk Installation

ADA Accessible Ramps Poured

Next Week:

Phase 1A Washington Street

Monday 4/21 to Friday 4/25 – Contractor to continue storm sewer installation along Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

In the upcoming weeks Main Street will be closed for pavement removal.

Once the utility crew finishes installing the storm sewer along Washington Street, they will shift their focus to Main Street to begin installing the new water main. Meanwhile, on Washington Street TK Concrete will focus on surface improvements, including road preparation, pouring new pavement, completing the remaining sidewalks, and installing permeable pavers in the on-street parking areas.

Follow along here to see the latest progress!

Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...