DIGGIN' DOWNTOWN UPDATE - 4/25

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 25, 2025 

Recent Weeks:
Storm Sewer Installation

Next Week:
Phase 1A Washington Street
(Monday 4/28 to Friday 5/2) 
Contractor to continue storm sewer installation along Washington Street.
Looking Ahead: 
Washington Street will remain closed as storm sewer installation continues through the following weeks. After storm sewer installation has been completed the contractor will begin subgrade preparation.
In the upcoming weeks Main Street will be closed for pavement removal to allow for the installation of the new water main and water service lines to the buildings.
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...