DIGGIN' DOWNTOWN UPDATE - 5/12

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 9, 2025

Recent Weeks:

Storm Sewer Installation

Subgrade Preparation

Next Week:

Phase 1A Washington Street

Monday 5/12 to Friday 5/16  – Contractor to continue storm sewer installation on west side of Fillmore Street and subgrade preparation on east side of Washington Street. Contractor will begin installing subbase on east side of Washington Street toward the end of the week.

Phase 1B Main Street

Monday 5/12 Main Street will be closed to traffic as the contractor begins pavement removals.

Looking Ahead:

Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks.


DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...