DIGGIN' DOWNTOWN UPDATE - 5/12

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 9, 2025

Recent Weeks:

Storm Sewer Installation

Subgrade Preparation

Next Week:

Phase 1A Washington Street

Monday 5/12 to Friday 5/16  – Contractor to continue storm sewer installation on west side of Fillmore Street and subgrade preparation on east side of Washington Street. Contractor will begin installing subbase on east side of Washington Street toward the end of the week.

Phase 1B Main Street

Monday 5/12 Main Street will be closed to traffic as the contractor begins pavement removals.

Looking Ahead:

Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks.


Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...