DIGGIN' DOWNTOWN UPDATE - 5/16

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 16, 2025

Recent Weeks:

Storm Sewer Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Saturday 5/17 – Contractor to be on site to continue paving operations on Washington Street.

Monday 5/19 to Friday 5/23 – Contractor to continue paving operations, begin sidewalk installation, and begin subdrain installation on east side of Washington Street. Contractor to begin subdrain installation and subgrade preparation on west side of Washington Street.

Phase 1B Main Street

Monday 5/19 to Friday 5/23 Contractor to complete pavement removals on Main Street.

Looking Ahead:

Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

Diggin' Downtown Update 11/26Date: November 26, 2025 Recent Weeks: Underground Utility Service Installation (West Jefferson St) Subgrade Compaction, Subbase, Subdrai...
Diggin Downtown Update 11/21Date: November 21, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Subgrade Compaction, Subbase, Subdrain Ins...
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
Diggin Downtown Update - 11/14Date: November 14, 2025 Recent Weeks: Underground Utility Service Installation (W Jefferson St) Subgrade Compaction, Subbase and Subdrai...