DIGGIN' DOWNTOWN UPDATE - 5/16
Date: May 16, 2025
Recent Weeks:
Storm Sewer Installation (Washington St)
Concrete Paving Operations (Washington St)
Pavement Removals (Main Street)
Next Week:
Phase 1A Washington Street
Saturday 5/17 – Contractor to be on site to continue paving operations on Washington Street.
Monday 5/19 to Friday 5/23 – Contractor to continue paving operations, begin sidewalk installation, and begin subdrain installation on east side of Washington Street. Contractor to begin subdrain installation and subgrade preparation on west side of Washington Street.
Phase 1B Main Street
Monday 5/19 to Friday 5/23 – Contractor to complete pavement removals on Main Street.
Looking Ahead:
Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.