Recent Weeks:

Storm Sewer Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Saturday 5/17 – Contractor to be on site to continue paving operations on Washington Street.

Monday 5/19 to Friday 5/23 – Contractor to continue paving operations, begin sidewalk installation, and begin subdrain installation on east side of Washington Street. Contractor to begin subdrain installation and subgrade preparation on west side of Washington Street.

Phase 1B Main Street

Monday 5/19 to Friday 5/23 Contractor to complete pavement removals on Main Street.

Looking Ahead:

Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

DIGGIN' DOWNTOWN UPDATE - 5/16Date: May 16, 2025 Recent Weeks: Storm Sewer Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (...
DIGGIN' DOWNTOWN UPDATE - 5/12Date: May 9, 2025 Recent Weeks: Storm Sewer Installation Subgrade Preparation Next Week: Phase 1A Washington Street Monday 5/12 to Frida...
DIGGIN' DOWNTOWN UPDATE - 5/2Date: May 2, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 5/5 to Tuesday 5/6 – Contractor to...
Cutting the Ribbon, Firing Up the Grills: Niemann Ace Ha... Osceola, IA – April 25, 2025 — Osceola Chamber Main Street proudly celebrated the grand opening of Niemann Ace Hardware with an official...