DIGGIN' DOWNTOWN UPDATE - 5/16

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 16, 2025

Recent Weeks:

Storm Sewer Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Saturday 5/17 – Contractor to be on site to continue paving operations on Washington Street.

Monday 5/19 to Friday 5/23 – Contractor to continue paving operations, begin sidewalk installation, and begin subdrain installation on east side of Washington Street. Contractor to begin subdrain installation and subgrade preparation on west side of Washington Street.

Phase 1B Main Street

Monday 5/19 to Friday 5/23 Contractor to complete pavement removals on Main Street.

Looking Ahead:

Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...