DIGGIN' DOWNTOWN UPDATE - 5/23

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 23, 2025


Recent Weeks:

Subdrain Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to continue subdrain installation and prepare for paving at intersection of Fillmore and Washington Street.

Phase 1B Main Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to begin storm sewer utility work.

Looking Ahead: Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
Diggin' Downtown Update 11/26Date: November 26, 2025 Recent Weeks: Underground Utility Service Installation (West Jefferson St) Subgrade Compaction, Subbase, Subdrai...
Diggin Downtown Update 11/21Date: November 21, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Subgrade Compaction, Subbase, Subdrain Ins...
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...