Recent Weeks:

Subdrain Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to continue subdrain installation and prepare for paving at intersection of Fillmore and Washington Street.

Phase 1B Main Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to begin storm sewer utility work.

Looking Ahead: Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

DIGGIN' DOWNTOWN UPDATE - 7/3Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer installation (Washingt...
DIGGIN' DOWNTOWN UPDATE - 6/27Date: June 27, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN UPDATE - 6/20Date: June 20, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Permeable Paver Insta...
Ribbon Cutting Celebrates Plant Therapy Co.'s Grand Open... On June 20 , Osceola Chamber-Main Street and community members gathered to celebrate the grand opening of Plant Therapy Co. at 203 S. Ma...