DIGGIN' DOWNTOWN UPDATE - 5/30

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: May 30, 2025 

Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)

Next Week:
Phase 1A Washington Street Monday 6/2 to Friday 6/6 – Contractor to continue subdrain installation and concrete paving along Washington Street.

Phase 1B Main Street Monday 6/2 to Friday 6/6– Contractor to install storm sewer utility.

Looking Ahead:
Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.
Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...