DIGGIN DOWNTOWN UPDATE - 6/13

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: June 13, 2025 
Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)
Storm Sewer Installation (Main Street)

Next Week:
Phase 1A Washington Street
Monday 6/16 to Friday 6/20 – Final touches on PCC pavement work on Washington Street West of the Fillmore Intersection
Contractor to continue driveway, sidewalk, curb and gutter for Washington Street East of Fillmore Intersection
Subbase and subdrain operations in preparation for permeable pavers

Phase 1B Main Street
Monday 6/16 to Friday 6/20– Contractor to continue storm sewer utility installation and begin water main installation.

Looking Ahead:
Washington Street will remain closed as paving operations and permeable paver preparation continue throughout the following weeks. Main Street will remain closed for utility installation.
Tentative Schedule - The week of July 7 to begin installation of sanitary and water service lines to the buildings along Main Street (this is when sidewalk and water interruptions would occur).
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...