DIGGIN' DOWNTOWN UPDATE - 6/27

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: June 27, 2025 

Recent Weeks:
-Concrete Paving Operations (Washington St)

-Permeable Paver Installation (Washington St)

-Storm Sewer installation (Main Street)


Next Week:
Phase 1A Washington Street
Monday 6/30 to Thursday 7/3 – Contractor to continue permeable paver and curb and gutter installation along Washington Street. Contractor to backfill behind the curb on the west end of Washington Street.

Phase 1B Main Street
Monday 6/30 to Thursday 7/3 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street.
*There will be no work completed on Friday July 4th.

Looking Ahead:
Washington Street will remain closed as paving and utility operations continue throughout the following weeks. Main Street will remain closed for utility installation.
The tentative start date for water service hookups to Main Street buildings, originally set for the week of July 7, is now expected to take place toward the end of July.
DIGGIN DOWNTOWN UPDATE - 6/19Date: June 19, 2026 Recent Weeks: The square is now all open to traffic! Sidewalk Installation (Fillmore St) Light Pole Installation (Fi...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...