DIGGIN' DOWNTOWN UPDATE - 6/27

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: June 27, 2025 

Recent Weeks:
-Concrete Paving Operations (Washington St)

-Permeable Paver Installation (Washington St)

-Storm Sewer installation (Main Street)


Next Week:
Phase 1A Washington Street
Monday 6/30 to Thursday 7/3 – Contractor to continue permeable paver and curb and gutter installation along Washington Street. Contractor to backfill behind the curb on the west end of Washington Street.

Phase 1B Main Street
Monday 6/30 to Thursday 7/3 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street.
*There will be no work completed on Friday July 4th.

Looking Ahead:
Washington Street will remain closed as paving and utility operations continue throughout the following weeks. Main Street will remain closed for utility installation.
The tentative start date for water service hookups to Main Street buildings, originally set for the week of July 7, is now expected to take place toward the end of July.
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...