DIGGIN' DOWNTOWN UPDATE - 6/27

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: June 27, 2025 

Recent Weeks:
-Concrete Paving Operations (Washington St)

-Permeable Paver Installation (Washington St)

-Storm Sewer installation (Main Street)


Next Week:
Phase 1A Washington Street
Monday 6/30 to Thursday 7/3 – Contractor to continue permeable paver and curb and gutter installation along Washington Street. Contractor to backfill behind the curb on the west end of Washington Street.

Phase 1B Main Street
Monday 6/30 to Thursday 7/3 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street.
*There will be no work completed on Friday July 4th.

Looking Ahead:
Washington Street will remain closed as paving and utility operations continue throughout the following weeks. Main Street will remain closed for utility installation.
The tentative start date for water service hookups to Main Street buildings, originally set for the week of July 7, is now expected to take place toward the end of July.
DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...