DIGGIN' DOWNTOWN UPDATE - 7/3
Date: July 3, 2025
Recent Weeks:
Concrete Paving Operations (Washington St)
Permeable Paver Installation (Washington St)
Storm Sewer installation (Washington Street/Main Street)
General Site Cleanup (Prior to 4th of July Celebration)
West Washington Intersection Opened (Washington Street)
Next Week:
Phase 1A Washington Street
Monday 7/7 to Friday 7/11 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.
Phase 1B Main Street
Monday 7/7 to Friday 7/11 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street. Contractor will move to utility installation along East Washington Street toward the end of the week.
*Scheduled water service interruption along Main Street will occur on Monday July 7.
Looking Ahead:
Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.