DIGGIN' DOWNTOWN UPDATE - 7/3

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: July 3, 2025

Recent Weeks:

Concrete Paving Operations (Washington St)

Permeable Paver Installation (Washington St)

Storm Sewer installation (Washington Street/Main Street)

General Site Cleanup (Prior to 4th of July Celebration)

West Washington Intersection Opened  (Washington Street)

Next Week:

Phase 1A Washington Street

Monday 7/7 to Friday 7/11 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.

Phase 1B Main Street

Monday 7/7 to Friday 7/11 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street. Contractor will move to utility installation along East Washington Street toward the end of the week.

*Scheduled water service interruption along Main Street will occur on Monday July 7.

Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.

Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...
Ribbon Cut & Doors Open at Urban LabelsDowntown Osceola just got a whole lot more stylish! On Tuesday, October 1, we celebrated the grand opening and ribbon cutting of Urban L...
Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...