DIGGIN' DOWNTOWN UPDATE - 7/3

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: July 3, 2025

Recent Weeks:

Concrete Paving Operations (Washington St)

Permeable Paver Installation (Washington St)

Storm Sewer installation (Washington Street/Main Street)

General Site Cleanup (Prior to 4th of July Celebration)

West Washington Intersection Opened  (Washington Street)

Next Week:

Phase 1A Washington Street

Monday 7/7 to Friday 7/11 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.

Phase 1B Main Street

Monday 7/7 to Friday 7/11 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street. Contractor will move to utility installation along East Washington Street toward the end of the week.

*Scheduled water service interruption along Main Street will occur on Monday July 7.

Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.

Osceola175 - Honoring Community ServiceDid you know one of Osceola’s most meaningful traditions began more than 75 years ago? In 1950, the Community Service Award was establis...
Nominations Are Now Being Accepted for the Annual Commun... This prestigious award was initiated in 1950 by Osceola Rotary Chapter and Osceola Chamber - Main Street to recognize an individual with...
DIGGIN DOWNTOWN UPDATE - 1/30/26Date: January 30, 2026 Recent Weeks: Sanitary Sewer Installation (Jefferson St) Next Week: Phase 2A Jefferson Street. Monday 2/2 to Frid...
2025 By the Numbers: Ribbon CuttingsAs we look back on 2025, one thing is clear: it was a year of growth, momentum, and new beginnings for Osceola. Throughout the year, ent...