DIGGIN' DOWNTOWN UPDATE - 7/11

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: July 11, 2025

 

Recent Weeks:

Roadway Extended East to Intersection (Washington St)

Permeable Paver Installation (Washington St)

West Washington Intersection Opened (Washington Street)

Intakes Installed (Main Street)

Storm Sewer Installation (Washington Street/Main Street)


Next Week:

Phase 1A Washington Street

Monday 7/14 to Friday 7/18 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.

Phase 1B Main Street

Monday 7/7 to Friday 7/11 – Storm sewer installation along East Washington


Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.


DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...