DIGGIN' DOWNTOWN UPDATE - 7/11
Date: July 11, 2025
Recent Weeks:
Roadway Extended East to Intersection (Washington St)
Permeable Paver Installation (Washington St)
West Washington Intersection Opened (Washington Street)
Intakes Installed (Main Street)
Storm Sewer Installation (Washington Street/Main Street)
Next Week:
Phase 1A Washington Street
Monday 7/14 to Friday 7/18 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.
Phase 1B Main Street
Monday 7/7 to Friday 7/11 – Storm sewer installation along East Washington
Looking Ahead:
Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.