DIGGIN' DOWNTOWN UPDATE - 7/11

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: July 11, 2025

 

Recent Weeks:

Roadway Extended East to Intersection (Washington St)

Permeable Paver Installation (Washington St)

West Washington Intersection Opened (Washington Street)

Intakes Installed (Main Street)

Storm Sewer Installation (Washington Street/Main Street)


Next Week:

Phase 1A Washington Street

Monday 7/14 to Friday 7/18 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.

Phase 1B Main Street

Monday 7/7 to Friday 7/11 – Storm sewer installation along East Washington


Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.


DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...