DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEW

- Remainder of July
- East Washington utility work
- Washington street pavers and concrete operations
- Subgrade prep on Main/Washington Intersection
- Week of August 4
- Water main installation on Main Street
- Paving operations at the Main Street/Washington intersection and East Washington
- Week of August 11
- Water service installation for buildings on Main Street
- Businesses along Main Street will experience some sidewalk interruptions during this time, depending on where your service line enters your building. Once work is complete, areas will be backfilled with rock.
- Closure of the Jefferson & Main Street intersection for pavement removals
- East Jefferson closed for pavement removals
- Week of August 18
- Sanitary service installation for buildings on Main Street
- Sidewalk access may again be impacted depending on service line locations into your building
- Paving operations on East Washington
- Week of August 25
- Finish concrete operations on East Washington
- Begin grading and subgrading on Main Street
- Begin utility work on East Jefferson
- Month of September
- Utility work on East Jefferson
- Paving operations on Main Street
- Week of October 6
- Jefferson Street West of Main Street closed for pavement removals