DIGGIN DOWNTOWN UPDATE - 7/25

Last Updated 7/28/2025Posted in DIGGIN' DOWNTOWN

Date: July 25, 2025

 Recent Weeks:

Concrete Paving Operations (Washington St)

Permeable Paver Installation (Washington St)

Storm Sewer installation (Washington Street/Main Street)

Water Main Installation (Washington Street/Main Street)

Next Week:

Phase 1A Washington Street

Monday 7/28 to Friday 8/1 – Contractor to continue permeable paver and sidewalk installation along Washington Street. Subgrade prep on Main/Washington Intersection.

Phase 1B Main Street

Monday 7/28 to Friday 8/1 – Contractor to continue water main and water service installation along East Washington Street.

Looking Ahead:

Washington Street will remain closed as sidewalk and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.


DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...
DIGGIN' DOWNTOWN UPDATE - 7/18Date: July 18, 2025 Recent Weeks: (Washington Street/Main Street) Storm Sewer installation Permeable Paver Installation (Washington St) ...
DIGGIN' DOWNTOWN UPDATE - 7/11Date: July 11, 2025 Recent Weeks: Roadway Extended East to Intersection (Washington St) Permeable Paver Installation (Washington St) Wes...