Date: August 8, 2025 
Recent Weeks:
Concrete Paving Operations (Washington & Main St)
Underground Utility Installation (Washington Street/Main Street)


Next Week:
Phase 1A Washington Street
Monday 8/11 to Friday 8/15 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street

Phase 1B Main Street
Monday 8/11 to Friday 8/15 – Contractor to continue water main installation along Main Street.

Looking Ahead:
Week of August 11 and 18: Water main installation on Main Street and paving operations on East Washington
Week of August 25: Jefferson/Main Intersection and East Jefferson closed for removals. Water services for Main Street businesses.
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...