DIGGIN DOWNTOWN UPDATE - 8/15
Date: August 15, 2025
Recent Weeks:
Pavement Removals (Jefferson St & Main St)
Underground Utility Installation (Main St)
Next Week:
Phase 1A Washington Street
Monday 8/18 to Friday 8/22 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street.
Phase 1B Main Street
Monday 8/18 to Friday 8/22 – Contractor to continue water main installation at Jefferson and Main Street intersection. Begin service installations along Main Street.
*Please note – Sections of sidewalk along Main Street will be inaccessible while sanitary and water service installation is underway.
Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continue throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.