DIGGIN DOWNTOWN UPDATE - 8/15

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: August 15, 2025 

Recent Weeks:
Pavement Removals (Jefferson St & Main St)
Underground Utility Installation (Main St)

Next Week:
Phase 1A Washington Street
Monday 8/18 to Friday 8/22 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street.
Phase 1B Main Street
Monday 8/18 to Friday 8/22 – Contractor to continue water main installation at Jefferson and Main Street intersection. Begin service installations along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while sanitary and water service installation is underway.

Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continue throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...