DIGGIN DOWNTOWN UPDATE - 8/15

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: August 15, 2025 

Recent Weeks:
Pavement Removals (Jefferson St & Main St)
Underground Utility Installation (Main St)

Next Week:
Phase 1A Washington Street
Monday 8/18 to Friday 8/22 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street.
Phase 1B Main Street
Monday 8/18 to Friday 8/22 – Contractor to continue water main installation at Jefferson and Main Street intersection. Begin service installations along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while sanitary and water service installation is underway.

Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continue throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.
Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...