DIGGIN DOWNTOWN UPDATE - 8/15

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: August 15, 2025 

Recent Weeks:
Pavement Removals (Jefferson St & Main St)
Underground Utility Installation (Main St)

Next Week:
Phase 1A Washington Street
Monday 8/18 to Friday 8/22 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street.
Phase 1B Main Street
Monday 8/18 to Friday 8/22 – Contractor to continue water main installation at Jefferson and Main Street intersection. Begin service installations along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while sanitary and water service installation is underway.

Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continue throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...